Assembly instruction internal staircase
Fitting of external covering profile between Ground and First floor
Staircase ready for fitting
Staircase breakthrough
GTX CONTAINEX
Assembly of platform
4 pieces of 6 x 80 mm screws
Setting of the first staircase part
Stair string aligned with platform
Stair piece screwed with 1 no. 6 x 80 mm screw
Insulate floor and roof frame
Fitting of condensation sheet
GTX CONTAINEX
Seal foil air-tight
Cover plates
Drilling of holes using 4,5 mm drill
Fastening of cover plates with 4,5 x 30 mm screws
Fastening of H-profile on covering plates
Cut out the recess in the cover plate for the floor fames and fit
GTX CONTAINEX
Cut outs for the sheet steel corner plate in the covering plates
Adjusting of the cover plates
Fitting of the corner trims
Fitting of the end profile on the first floor with Silicon
Hand rail post to be mounted on the top stair, watch the alignment
2 pieces of $6 \times 80 \mathrm{~mm}$ screws
GTX CONTAINEX
2 pieces of screws 6 x 80 mm
Positioning of top stair run
1 piece screw 6 x 80 mm
Removal of the transport protection from the hand rails
Positioning of the centre post
3 pieces of screws 6 x 80 mm
Fastening of the hand rail frame with 2 pieces 6 x 80 mm screws
GTX CONTAINEX
2 pieces of 6 x 80 mm screws on the centre post
Fastening with screws 6 x 100 mm on the stair string
Positioning and fastening of the balustrade with 5 pieces of screws 6 x 120 mm
Fastening of the newel with 5 pieces 6 x 120 mm screws and the bottom rail frame
Platform fastened with the delivered distance pieces onto the wall panels with 6 x 120 mm screws
CTA CONTAINEX
Hand rail fastened 100 cm above rail string with the delivered distance pieces on the walls with 3 screws 6 a 120 mm for each rail
Fastening of the platform with 4 pieces 6 a 100 mm screws